STRUCTURAL RECONSTRUCTION OF THE AGI-BES HALILI BUILDING | TIRANA


During the inspection, slight damage to the internal wall and moderate damage to the partition walls on the external facade of the Block, as well as damage to the existing columns, were encountered. The C-FRP method is used, which serves to increase the bearing capacity of the element in the case of beams or columns, this method means reinforcing the beams with carbon fibers.

Some of the works performed are:
- Reinforcement of concrete structures with C-FRP
- Brick wall repair
- Hydraulic plastic paint
- Electrical and plumbing repairs


See some photos during the structural rehabilitation works: